Method Statement and Risk Assessment Template

Use this method statement and risk assessment template to plan work before it starts. Describe the scope, choose the work category, rate complexity and estimate hours. Break the job into tasks with owners, list the hazards of each step and grade them from low to critical, then set controls to reduce each risk and sign off. Complete it on mobile and free in flowdit.

Use this template with flowdit

  • Customize this template or build your own
  • Complete inspections using the mobile app
  • Get reports and analyze your data

Start inspecting smarter — free for one user.

Method Statement and Risk Assessment Template
Based on

Using a method statement and risk assessment

  • Record the date the method statement is conducted, who prepared it, and the location of the work.
  • Describe the scope of work and classify the work category using the options provided, such as construction, maintenance, facility operations, engineering works, demolition, installation, or inspection.
  • Rate the complexity of the project and estimate the work duration in hours so the plan reflects the size of the job.
  • Break the work down into the tasks involved and describe them in detail.
  • Assign responsible personnel to the tasks so accountability is clear.
  • Identify the hazards and risks arising from those tasks.
  • Grade each risk using the severity scale, from low (minor injury possible) through medium (lost time injury possible) and high (serious injury or fatality possible) to critical (multiple fatalities possible).
  • Set out the control measures and mitigation strategies that will reduce each risk.
  • Sign off the document and record the time it was finished.

Start inspecting smarter — free for one user.

What a method statement and risk assessment is

A method statement and risk assessment is a pair of documents prepared before work begins. The method statement explains how the job will be done: what the scope is, what tasks are involved, who carries them out, and how long the work is expected to take. The risk assessment explains what could go wrong at each of those steps, how serious the outcome could be, and what is being done to control it. In many workplaces the two are combined into a single document, commonly known as RAMS.

This template supports both halves of that work. It opens with a method statement assessment and a method statement overview, then moves into a task breakdown and risk assessment. Doing the planning and the risk thinking together means the control measures you write down are tied to a specific task in a specific sequence, rather than sitting in a separate file.

Why it matters

Method statements and risk assessments exist so that risks are considered deliberately rather than discovered on site. Writing down the sequence of tasks forces you to think through how one activity hands over to the next, where people, plant, and materials interact, and which steps carry the greatest potential for harm.

A structured document also gives the people doing the work a shared reference point. When the tasks, the responsible personnel, the hazards, and the control measures are recorded in one place, a supervisor or inspector can check that the plan is being followed and that the controls described are actually in place. Grading risk by severity — from minor injury possible through to multiple fatalities possible — lets you see at a glance where the greatest attention is needed.

What a good method statement and risk assessment covers

  • Administrative detail. The date it was conducted, who prepared it, and the location of the work, so the document can be traced to a specific job.
  • Scope of work. A clear description of what the work includes, supported by a work category classification such as construction, maintenance, facility operations, engineering works, demolition, installation, or inspection.
  • Complexity and duration. A project complexity rating and an estimated work duration in hours, so the plan reflects the real size of the job.
  • Task breakdown. A detailed description of the tasks involved, in the order they will be carried out, with the responsible personnel identified for each.
  • Hazards and risks. The hazards that the task sequence creates, and a severity level for each: low (minor injury possible), medium (lost time injury possible), high (serious injury or fatality possible), or critical (multiple fatalities possible).
  • Control measures. The mitigation strategies that will reduce each risk, written specifically enough to be acted on.
  • Sign-off. A signature and a finished-at time to close the record, along with the real start and end dates of the inspection.

How to carry it out

  1. Complete the assessment details. Record the date, who prepared the document, and the location of the work.
  2. Describe the scope. Write a clear scope of work description, then classify the work category and rate the project complexity. Estimate the work duration in hours.
  3. Break the work into tasks. List the tasks involved and describe them in detail, in the sequence they will happen.
  4. Assign responsibility. Set out the responsible personnel for the tasks so it is clear who owns each part of the job.
  5. Identify hazards. For each task in the sequence, record the hazards and risks it presents.
  6. Grade the risk. Apply the severity scale to each risk so that the most serious outcomes are visible. Use the definitions in the scale — minor injury possible, lost time injury possible, serious injury or fatality possible, multiple fatalities possible — rather than a subjective label.
  7. Set out the controls. For every hazard you have identified, state the control measures and mitigation strategies that will reduce the risk. Keep them tied to the task they relate to.
  8. Sign off and close the record. Add the signature, the time the document was finished, and the real start and end dates of the inspection.
The value of this document comes from the link between the task breakdown and the control measures. A risk listed without a corresponding control, or a control that does not match the task it sits beside, leaves the gap that the document was meant to close.

Where it fits in a wider system

A method statement and risk assessment is normally one part of a broader approach to managing health and safety at work. Where a regulation or standard applies to your activity — for example OSHA requirements in the United States, or ISO and HACCP frameworks in the sectors that use them — the method statement and risk assessment is the document that shows how your specific job will be planned and controlled in line with those obligations. The template does not reproduce any regulation's requirements; it gives you a consistent structure in which to record your own scope, tasks, hazards, severity ratings, and control measures.

Because the format is consistent, the completed document can be reviewed by a project lead before work starts, checked by a supervisor while the work is under way, and audited by an inspector afterwards against the same tasks and controls. The record of the real start and end dates, together with the signature and completion time, makes that review possible.

Frequently Asked Questions

A method statement template is a structured document used to set out, before work begins, how a task will be carried out and how its risks will be managed. In practice it combines two things: a method statement that describes the scope, sequence, and duration of the work, and a risk assessment that records the hazards that sequence creates, their severity, and the control measures put in place. Together they are often referred to as RAMS. The template here begins with a method statement assessment and overview and then moves into a task breakdown and risk assessment, so the plan and the risk thinking are prepared together rather than separately.

This template covers three areas. The method statement assessment and method statement overview sections capture who prepared it, where the work is, the scope of work, the work category, the project complexity, and the expected duration. The task breakdown and risk assessment section then captures the detailed tasks involved, who is responsible for them, the identified hazards and risks, the risk severity level, and the control measures. Answer scales in the template allow the work to be classified (for example construction, maintenance, or facility operations) and the risk severity to be graded from minor injury possible through to multiple fatalities possible.

Use the method statement assessment and overview fields to record the date, the person preparing the document, the location of the work, the scope of work description, the work category classification, the project complexity rating, and the estimated work duration in hours. Completion guidance is provided within the template. Add the detailed description of tasks involved and the responsible personnel so the sequence of work and accountability for each step are both explicit.

Break the work into the tasks involved and describe them in detail, then list the hazards and risks each task presents. Record the risk severity level using the scale provided, which runs from low (minor injury possible) through medium (lost time injury possible) and high (serious injury or fatality possible) to critical (multiple fatalities possible). For each hazard, set out the control measures and mitigation strategies that will bring the risk down. This keeps the method statement connected to the risk assessment rather than treating them as two unrelated documents.

This template is built for the people who plan and review work before it starts: safety managers, project leads, and inspectors. It is intended for use across construction, maintenance, and facility management operations, and it includes classification options for engineering works, demolition, installation, and inspection as well as an other category.

It should be prepared before the project commences, in line with the template's purpose of establishing control measures prior to work starting. The overview captures the date it was conducted, and the record is closed out with a signature and a finished-at time. The template also records the actual start and end dates of the inspection, so the planned document and the work as it was carried out can both be traced.
Arne Reis
Written by
Arne Reis
Founder
Process optimizer with 25 years of expertise, focused on operational excellence in quality, maintenance, EHS, and commissioning. Emphasizes innovative solutions and top-quality standards.
View LinkedIn profile

Still managing operations with paper and Excel?

Digitize inspections, audits, SOPs, and corrective actions.

Book A Personal Demo
flowdit mobile inspection app

Ready to simplify inspections and get your team moving faster?

Start free today and turn inspections into a clear, consistent digital workflow. Prefer a guided walkthrough? Book a demo and see how flowdit can fit your team.