Construction Site Shutdown and Mothballing Checklist
This checklist provides construction teams with a structured framework to plan, execute, and document the temporary shutdown or mothballing of construction sites. It addresses key areas including insurer notifications, risk assessment updates, emergency response readiness, and comprehensive site security measures. The checklist offers detailed guidance on maintaining proper housekeeping standards, removing waste and combustible materials, isolating non-essential utilities, and ensuring alarm systems remain active. It also covers safe storage of plant and machinery, crane safety protocols, statutory inspection scheduling, and the proper de-energising of installed equipment. Additional sections address water damage prevention, earthworks and drainage management, and ongoing temporary works maintenance. Use this tool to systematically record all actions taken, schedule periodic inspections, and ensure a safe, controlled, and well-documented site restart.
Use this template with flowdit
- Customize this template or build your own
- Complete inspections using the mobile app
- Get reports and analyze your data
Start inspecting smarter — free for one user.
How to Use This Checklist
- Notify your insurer and insurance broker in writing that site operations will cease for an extended period, and review and update the Project/Site Emergency Response Plan to reflect the shutdown. Prepare a documented Project Recommencement Plan for the return to operations, and keep the Project Risk Register reviewed and updated at appropriate intervals.
- Confirm the site will remain enclosed by an adequate, robust security fence for the whole shutdown. Check that remotely monitored CCTV covers the perimeter and critical internal areas, is connected to an approved 24-hour manned Alarm Receiving Centre, and includes PIR movement sensors and a voice challenge facility operated from the CCTV control room. Confirm intruder alarms and automatic fire alarms remain operational and connected.
- Clear waste and combustible materials, minimise storage inside buildings, and keep storage areas away from flood-risk zones. Raise stored equipment and materials off the ground, and remove fuel oils and gas cylinders from site or store them securely outside. Isolate all non-essential utilities and services to reduce risk during the shutdown.
- Remove construction plant from site or park and store it in a secure compound outside any flood risk zone. Remove keys and batteries from large plant. Shut down and de-energise electro-mechanical installations in line with the manufacturer's instructions, keep plant rooms free of combustible materials and secure them, and ensure fixed fire protection systems remain fully operational. Store and preserve any uninstalled electro-mechanical equipment to the manufacturer's recommendations, covering it with flame-resistant materials such as those meeting LPS 1207 or equivalent where possible.
- Verify that premises are fully water-tight, isolate and drain down water systems and supplies, and install remotely monitored leak detection where water systems stay active. Display the locations of water shut-off valves and stopcocks on a site plan at the main site entrance. Clear and secure earthworks storage areas, protect exposed earthworks, keep drainage runs flowing freely, and maintain pumps and dewatering systems with documented arrangements and, where critical, remotely monitored alarms.
- Complete structural reviews and risk assessments for all temporary works remaining on site, assess wind loadings including any temporary covering materials, and set out arrangements for regular inspection and maintenance of temporary works and re-assessment of structural integrity during the shutdown. Document all actions, schedule periodic inspections, and record the results so the site is safe, controlled, and ready for a well-documented restart.
Start inspecting smarter — free for one user.
How to use this checklist
The checklists should be used