Commissioning Checklist

This commissioning checklist ensures the safety and effectiveness of new or modified systems within a facility. Use this comprehensive list to efficiently validate the performance of HVAC equipment, pumps, piping, and lighting systems. The checklist includes required installation checks as well as points for Testing, Adjusting, and Balancing (TAB).

Use this template with flowdit

  • Customize this template or build your own
  • Complete inspections using the mobile app
  • Get reports and analyze your data

Start inspecting smarter — free for one user.

Commissioning Checklist
Based on

How to Use This Checklist

  • **Confirm installation and access.** Check the enclosure for dents, leaks, and door seals; confirm access doors close tightly, the casing between shaft and unit is complete, and vibration isolation devices are installed and released from shipping locks. Verify maintenance access to unit and components is available.
  • **Check thermal, instrumentation, and cleanliness items.** Confirm sound attenuation and insulation are installed as specified; instrumentation such as thermometers, pressure gauges, and flow meters is installed per specification; filters are installed with type and efficiency permanently noted; coils are clean with fins in good condition; condensate pans are clean and sloped toward the drain; and equipment cleaning is complete per contractual documents.
  • **Verify refrigerant and pipework integrity.** Check that no leaks are visible at refrigerant fittings. Confirm pipe connections are fully and properly supported, taking thermal expansion and building expansion joints into account, and that installed safety devices are functional, shown to be leak-tight, and that any special requirements are met so the system is functional.
  • **Test and adjust (TAB).** Position and secure OSAT, MAT, SAT, and RAT sensors and confirm sensors are calibrated. Ensure controller locations and connections are checked and components are inspected for physical integration. Calibrate and record motor overload settings, and observe pump operation to confirm implemented safeguards function as specified.
  • **Review electrical and safety provisions.** Confirm safety devices are installed and safe operating ranges are provided; that isolators are present and properly labelled; that all electrical connections are secure and present; and that any deviations from the commissioned work flows are noted.
  • **Document outcomes.** Record operational events and submitted documentation against the commissioned work flows, and report incidents and records according to the set protocols.
  • **Sign off.** Capture the conducted-on date, who prepared it, the location, the signature, the finish time, and the actual inspection start and end dates.

Start inspecting smarter — free for one user.

What commissioning verification covers

Commissioning is the step where you prove that a newly installed or modified system is safe and performs the way it was designed to. Rather than testing a system after it is already in regular use, commissioning verifies it at the point where the equipment, controls, and balancing work can still be corrected. This checklist treats the facility as a set of connected systems — HVAC equipment, pumps, piping, and lighting — and takes you through the installation and Testing, Adjusting, and Balancing (TAB) checks for each.

Installation checks

Before any system is run, you confirm that it has been built as specified. This includes the physical condition of equipment: enclosures free of dents, leaks, and door seal defects; access doors that close tightly; complete casing between shaft and unit; vibration isolation devices installed and released from shipping locks; and adequate maintenance access to the unit and its components. Sound attenuation, insulation, and instrumentation must be installed in line with the specification. Cleanliness matters too — equipment is cleaned per the contractual documents, filters are installed with their type and efficiency permanently noted, coils are clean with fins in good condition, and condensate pans are clean and sloped toward the drain.

TAB: testing, adjusting, and balancing

TAB is where the system is brought to its design operating condition. The checklist guides you through positioning and securing the OSAT, MAT, SAT, and RAT sensors and confirming they are calibrated, checking controller locations and connections, and inspecting components for physical integration. Motor overload values need to be calibrated and recorded with no deviations, and pump operation needs to be observed with its safeguards confirmed to work as specified. Where the system has refrigerant fittings, you check that no leaks are visible; where pipework is installed, you confirm connections are properly supported, including allowances for thermal expansion and building expansion joints.

Electrical and safety provisions

Safety devices must be installed and operating ranges confirmed safe, and the system shown to be functional. Isolators need to be present and properly labelled, and all electrical connections secure and present. Record any incidents and maintain records as required by the set protocols.

Documenting results

Each checklist item is answered as pass, fail, or not applicable, and the record captures the date, the person preparing it, the location, the signature, the finish time, and the actual inspection start and end dates. Where operational events, submitted documentation, or the commissioned work flows show a deviation, note it so the responsible party can act on it.

Common pitfalls

- **Treating commissioning as a paperwork exercise.** The value is in the field checks: enclosures, seals, piping supports, sensor calibration, motor overload settings, and pump behaviour. - **Leaving vibration isolation shipping locks in place.** They must be released before the unit is run, otherwise the isolation does not work as designed. - **Skipping cleanliness before start-up.** Filters, coils, and condensate pans should be clean and correct before testing begins. - **Balancing without checking the sensors first.** OSAT, MAT, SAT, and RAT sensors must be positioned, secured, and calibrated before the TAB readings mean anything. - **Ignoring documentation discrepancies.** Deviations from submitted documentation and commissioned work flows should be recorded, not passed over.

Who this is for

Commissioning agents, mechanical and electrical contractors, facilities engineers, and building operators can use this checklist to verify HVAC equipment, pumps, piping, and lighting systems before handover, and to keep a consistent record of what was checked and what was found.

Why it matters

A system that is commissioned properly is less likely to surprise you once it is in service. Verifying installation, TAB results, electrical connections, and safety provisions together confirms that equipment operates as specified and that safe operating ranges are in place. The record produced by the checklist also gives you a clear reference point for future maintenance and troubleshooting.

Frequently Asked Questions

Commissioning is the process of verifying that a new or modified system has been installed correctly and performs as intended before it is placed into service. This checklist walks through installation checks and Testing, Adjusting, and Balancing (TAB) points for HVAC equipment, pumps, piping, lighting systems, and related components, so you can confirm both safety and performance.

Commissioning verification matters because it confirms that equipment is installed as specified, operates within safe ranges, and that performance issues are found before systems go into regular use. The checklist covers installation, TAB, and documentation together, so you can address problems while the relevant work is still open to correction.

It should be carried out before handover of the new or modified system. Complete the installation checks and TAB points for each unit of equipment, record the outcome for each item, and note any deviations from the specified operating flows or documentation. Where safety devices, interlocks, or pump controls are involved, confirm they are functional and that the system behaves as intended.

No. The checklist references contractual documents and specifications, but it does not name specific legal standards or regulations. Follow the applicable requirements for your jurisdiction and project alongside this checklist.
Arne Reis
Written by
Arne Reis
Founder

Process optimizer with 25 years of expertise, focused on operational excellence in quality, maintenance, EHS, and commissioning. Emphasizes innovative solutions and top-quality standards.

View LinkedIn profile

Still managing operations with paper and Excel?

Digitize inspections, audits, SOPs, and corrective actions.

Book A Personal Demo
flowdit mobile inspection app

Ready to simplify inspections and get your team moving faster?

Start free today and turn inspections into a clear, consistent digital workflow. Prefer a guided walkthrough? Book a demo and see how flowdit can fit your team.